Construction Updates

Please contact Kathy Jirschele at Kathy@kaneenpr.com or call 520.623.3073 if you have questions or comments regarding construction.

November 22, 2017

Thank you for your interest in the Tangerine Road Improvements.

The contractor will begin paving operations along several segments of Tangerine Road. The paving operation will begin on Wednesday, November 29, and is scheduled to be complete by Friday, December 22, 2017.

The work will include;

  • Placing the final lift of pavement on Tangerine Road, between Dove Mountain/Twin Peaks and Thornydale Road.
  • Place the final lift of pavement at Tangerine Road intersections of Dove Mountain/Twin Peaks and Thornydale Road.
  • The contractor will also place the base course of pavement on the westbound lanes of Tangerine Road, between La Cholla Boulevard and La Canada Drive and, eastbound Tangerine Road from Thornydale Road to La Cholla Boulevard.

On Friday, December 1, and Saturday, December 2, from 6 am to 5 p.m. each day, the contractor will place the final lift of pavement on the Tangerine Road intersection of Dove Mountain/Twin Peaks. Because of the nature of this paving operation, the intersection will be closed to all vehicular, pedestrian and bicycle traffic.

  • Officers will be on site to direct traffic.
  • Motorist will be redirected around the work area.
  • Access to businesses in the area will be maintained.
  • Travelers in this area should plan for serious delays and use alternate routes.
  • The intersection will be re-opened to traffic at 5 p.m. each evening.

November 9, 2017

Thank you for your interest in the Tangerine Road Improvements

On Monday, November 13, the contractor will begin reconstruction of the northwest corner of the Tangerine Road/La Cholla Boulevard intersection. Traffic along Tangerine Road will be shifted to the south from just west of the La Cholla Boulevard intersection. The current traffic configuration through the intersection will generally remain the same with the following changes:

  • Turn movements in all directions are permitted, however
    • There will not be a dedicated right turn lane from eastbound Tangerine Road to southbound La Cholla Boulevard
    • Left-turn movements will have a dedicated lane in all directions.
  • Southbound La Cholla traffic, north of the Tangerine Road intersection, will be shifted to the east. There will not be a dedicated left-turn lane into the Church of the Apostles driveway.
  • Traffic remains reduced to one-lane in all directions.
  • Speed limits are reduced to 25 MPH.
  • Motorists should expect delays.

On Monday November 13, through Wednesday, November 16, the contractor will install traffic-signal loops at the Tangerine Road/Thornydale Road intersection.

Travelers in the area should expect:

  • Intermittent lane closures
  • Speed limits reduced to 25 MPH
  • Motorists should expect delays

As a reminder, please be aware of bicyclists and pedestrians in the area and ensure that dogs, horses and other animals are not in the construction zone to ensure the safety of all. Bicycles traveling through this area can use the full travel lane.

October 2017

At 10 p.m. on Monday, October 30, crews will shift east and westbound traffic to the new westbound travel lanes (north side) of Tangerine Road, from just west of Dove Mountain, east to Thornydale Road. Temporary pavement marking will also be installed.
Read More »

September 2017

Beginning at 5 a.m. on Monday, September 25 through 10 p.m. Wednesday, September 27, the contractor will complete paving operations in the intersection and adjacent roadways of Tangerine and Thornydale Roads.
Read More »

August 2017

On Wednesday, August 16, from 6 a.m. to 10 p.m., crews will pave a transitional path to the new westbound lanes of Tangerine Road at La Cholla Boulevard.
Read More »

July 2017

Beginning Monday, July 24, Tangerine Corridor Constructors will install signal loops on Camino de Manana at Tangerine Road. This work is scheduled from 6 a.m. to 4 p.m. each day and will continue through the end of the week, weather permitting.
Read More »

June 2017

Beginning Monday, June 26 through Thursday, June 29 (weather permitting) from 6 a.m. to 3 p.m. each day, Tangerine Corridor Constructors will pave the new westbound lanes of Tangerine Road from Dove Mountain/Twin Peaks to just west of Camino de Oeste.
Read More »

May 2017

Beginning Tuesday, May 30, from 6 a.m. to 4 p.m. each day, Tangerine Corridor Constructors will be installing traffic signal loops at the Tangerine Road and Dove Mountain Boulevard/Twin Peaks Road intersection. In addition, they will also be completing work in the median at the intersection.
Read More »

April 2017

On Tuesday, May 2, through Friday, May 5, from 7 a.m. to 4 p.m. each day, Tangerine Corridor Constructors will reconstruct the Tangerine Crossing exit at Tangerine Road.
Read More »

March 2017

Beginning Monday, April 3, through Wednesday, April 5, from 7 a.m. to 4 p.m. each day, Tangerine Corridor Constructors will be reconstructing access to Camino de Oeste, north of Tangerine Road.
Read More »

February 2017

Beginning Tuesday, February 21, through Friday, February 24, from 7 a.m. to 4 p.m. each day, there will be intermittent flagging operations along Tangerine Road from Camino de Mañana to La Cholla Boulevard to help direct traffic while the contractor installs utility crossings along Tangerine Road. Expect delays.
Read More »

January 2017

On Tuesday, January 31, from 7 a.m. to 4 p.m., the contractor will install utility infrastructure across Verch Way at Tangerine Road. The traveling public can anticipate the following impacts:
Read More »

December 2016

On Monday, December 5, from 7 a.m. to 5 p.m., the contractor will be working on waterlines at the Tangerine Crossing entrance at Tangerine Road.
Read More »

November 2016

Beginning 10 p.m., Tuesday, November 8, traffic will be shifted on Tangerine Road between Camino de Oeste and Thornydale Road to help facilitate the construction of the new alignment of Tangerine Road. This traffic control is scheduled to be in place for the next several months.
Read More »

September 2016

Thank you for your interest in the Tangerine Road improvements. Beginning Sunday night, September 25th from 8 pm to 5 am through early October, crews from Tangerine Corridor Constructors will begin working on utility crossings on Tangerine Road from Camino de Manana to Thornydale Road.
Read More »

August 2016

Crews will be working at the Tangerine Road and Twin Peaks/Dove Mountain intersection in preparation for the Tangerine Road…
Read More »

July 2016

Beginning Sunday night, July 10 from 8 pm to 5 am, crews from Tangerine Corridor Constructors will begin working on utility crossings…
Read More »

 

Tangerine Road
  • Tangerine Road Project c/o 100 N Stone Avenue, Ste. #450
  • Tucson, AZ 85701
  • Phone: 520.623.3073