Construction Updates for August 2017

August 11, 2017

Thank you for your interest in the Tangerine Road Improvements.

On Wednesday, August 16, from 6 a.m. to 10 p.m., crews will pave a transitional path to the new westbound lanes of Tangerine Road at La Cholla Boulevard. Residents and the traveling public can expect the following:

  • East and westbound traffic will be shifted to the south just west of La Cholla Boulevard
  • The speed limit will be reduced to 15 MPH
  • Expect delays

On Wednesday night, August 16, beginning at 10 p.m., crews will begin shifting traffic to the new westbound lanes of Tangerine Road and installing temporary pavement markings on Tangerine Road between Tangerine Crossings Drive and La Cholla Boulevard. Residents and the traveling public can expect the following:

  • East and westbound traffic will be shifted to the new westbound travel lanes of Tangerine Road from Tangerine Crossings Drive to La Cholla Boulevard
  • The speed limit will be 25 MPH
  • Expect delays

**Following this work traffic control will be significantly different, please take extra caution when driving through the area.**

August 4, 2017

Thank you for your interest in the Tangerine Road Improvements.

On Wednesday, August 9, from 6 a.m. to 6 p.m., the contractor will switch power to the new traffic signals and remove old traffic signals at the Tangerine Road and La Cholla Boulevard intersection. During this time, Oro Valley Police will be onsite to help direct traffic. Expect delays.

**UPDATED **
August 1 2017

July 27, 2017

Thank you for your interest in the Tangerine Road Improvements.

Beginning Monday, July 31 through Friday, August 4, from 6 a.m. to 4 p.m. each day, the contractor will work on waterlines on Camino de Oeste south of Tangerine Road. During this work, traffic will be shifted around the work area, allowing one lane in each direction. Resident access will be maintained during construction. Traffic control will be in place 24 hours a day.

Beginning Monday, July 31, the contractor will begin construction on the new northbound lanes of Thornydale Road. During this work, traffic will be shifted to the west on Thornydale Road south of Tangerine Road. Traffic will be maintained to one through lane in each direction and a left turn lane in each direction at the intersection of Thornydale Road and Tangerine Road. Traffic control will be in place 24 hours. Work is anticipated to be complete by mid-September.

Paving continues through Thursday, August 3 from 6 a.m. to 4 p.m. each day. The contractor is ahead of schedule paving the new westbound lanes of Tangerine Road from Tangerine Crossing Drive to La Cholla Boulevard. Beginning Wednesday August 2nd, paving will begin on side street entrances on the north side of Tangerine Road from Tangerine Crossing Drive to La Cholla Boulevard. Side streets will be intermittently closed as paving equipment progresses through the area. Please expect delays.

Beginning Wednesday, August 2nd, from 5:30 am - 3:00 pm, the southbound La Cholla left turn lane onto eastbound Tangerine will be closed. Left turns can be made from the southbound through lane. Watch for signage.

Beginning Thursday, August 3rd, from 5:30 am - 3:00 pm, the northbound La Cholla left turn lane onto westbound Tangerine will be closed. Left turns can be made from the northbound through lane. Watch for signage.

 